FAQs

Below you will find answers to a range of questions on our proposals for East Park Energy. We hope they answer your queries and we will continue to update them as our plans evolve.

If your question is not listed below, get in touch with the team using the details provided at the bottom of the page and a member of our team will be more than happy to assist you.


  • Background
  • Our proposals
  • The consultation process
  • The DCO process
Background
What is East Park Energy?

East Park Energy is a proposed ground-mounted solar energy generating station and battery energy storage system located to the northwest of St Neots. The project would connect up-to 400 megawatts of solar power, along with up-to 100 megawatts of battery storage, to the electricity transmission network at National Grid’s Eaton Socon substation. Our proposals also include associated infrastructure, works to create, enhance and maintain the natural environment, and a Legacy Fund that would provide financial contributions to local projects.  

We submitted a development consent order application seeking permission to build, operate and decommission the project on 3 October 2025. You can read more about our submitted plans here.

Who is Brockwell Storage and Solar?

Proposals for East Park Energy are being developed by Brockwell Storage and Solar, formerly known as RNA Energy. 

RNA Energy was acquired by Brockwell Energy in March 2024. Our aim is to develop a pipeline of solar and battery storage projects, contribute to Brockwell Energy’s goal of developing five gigawatts of installed renewable generation capacity by 2030, and to support the UK’s transition to net zero. 

At the heart of our mission to produce clean, renewable energy are the communities in which we hope to develop and invest. As a responsible, people-focussed company, we are committed to creating projects that bring long-term community benefits. This includes job creation, public access, recreational opportunities and ecological enhancement. 

You can find out more about Brockwell at brockwellstoragesolar.com or brockwellenergy.co.uk. 

What is solar power?

Solar power is generated through the conversion of energy from the sun into electricity. It’s a clean source of power, meaning that no carbon emissions are created by the panels during energy generation.

What is a battery energy storage system (BESS)?

A BESS stores electricity in batteries until it is needed by the electricity transmission network, at which point it is discharged into the network. Battery energy storage systems mean that during times of low demand, power from renewables such as solar can be stored until it is needed. This means that we can take advantage of solar power even when the sun isn’t shining. 

What's happened so far?

We held an initial non-statutory public consultation on our early plans for East Park Energy in autumn 2023. This was followed by a statutory public consultation on our detailed plans in autumn 2024.

Following this, our team has reviewed all feedback received alongside the results of environmental and technical assessments and engagement with stakeholders. Our final plans were submitted as part of a development consent order (DCO) application on 3 October 2025.

Why is East Park Energy needed?

The UK needs to take urgent action to respond to climate change and other factors, such as instability in global energy markets. The UK has a legally binding commitment to reduce carbon emissions to net zero (meaning that we will remove as much carbon from the atmosphere as we produce) by 2050, whilst Cambridgeshire County, Bedford Borough and Huntingdonshire District Councils all have their own net zero targets. 

As a country, we’ve already made a huge amount of progress towards meeting these targets. Government data shows that greenhouse gas emissions in the UK have fallen by 50% since 1990, but there’s a lot more still to do. Fossil fuels are still responsible for more than one quarter of the UK’s total electricity supply, whilst demand for electricity is forecast to roughly double between now and 2050. Renewable sources of energy, such as solar power, will be crucial to helping replace fossil fuel energy sources and to meeting future increases in energy demand. 

How much power will East Park Energy be capable of generating?

East Park Energy will be capable of connecting up-to 500 megawatts (MW) of power to the electricity transmission network at Eaton Socon substation. Up-to 400 MW will come from the solar development, whilst a further 100 MW will come from the battery energy storage system. 

What are the advantages of solar power?

Solar power is a clean source of electricity, meaning that no carbon emissions are created by the panels during electricity generation. Some of the other benefits associated with solar include: 

  • Solar power is cheaper to produce than fossil fuel sources of electricity 
  • Solar and battery storage support the UK’s energy security by providing more homegrown power 
  • Solar is generally quicker to build than other sources of renewable or low carbon power. 
There are already solar developments being built or in operation in this area, so why is East Park Energy required?

Whilst we recognise that there are existing and planned solar developments in this area, there is a need to continue to develop solar projects in order to meet government targets, including that of decarbonising the electricity transmission system and tripling the amount of solar power produced in the UK by 2030.  

Will the project reduce my energy bills?

Whilst East Park Energy will not reduce your energy bills overnight, it will contribute to boosting the UK’s energy security, which should help to reduce the volatility of energy prices in the future. Solar power is significantly cheaper to produce than power from fossil fuel sources.  

How big is the site?

Our proposals are split across an area totalling approximately 766 hectares in size. This figure includes all land required for the solar development, BESS facility, landscaping, cabling, access and grid connection.  

To make our proposals easier to understand, we have sub-divided them into four sites where above ground infrastructure would be located, along with linear corridors where underground cabling is proposed. You can find out more about this here.

Our proposals
What are your latest proposals for East Park Energy?
Following extensive engagement with the community and stakeholders, we submitted our Development Consent Order (DCO) application to the Planning Inspectorate on Friday 3 October 2025. The Planning Inspectorate formally accepted our application on Thursday 30 October 2025. All application documents are available to view on the Planning Inspectorate’s website and via our Document library. We’re grateful to everyone who provided feedback on our proposals during the pre-application process. As part of the Pre-examination phase, the relevant representation period is now open. This is your opportunity to take part in the Examination process by registering as an interested party and submitting a written summary of your views. The registration period opened on Wednesday 26 November 2025, and will close at 23:59 on Wednesday 14 January 2026. To register, you can submit a relevant representation via the Planning Inspectorate’s website.
What response did you get to the non-statutory consultation in 2023?

We received more than 370 pieces of feedback in response to last year’s consultation. Some of the recurring themes seen in this feedback included questions about the need for and location of the project, along with concerns about the potential impacts of the proposals on the environment, including the loss of agricultural land and impact on food security.  

All of this feedback, along with the results of ongoing technical assessments, has been carefully considered as part of the development of our proposals prior to the statutory consultation.  

You can read more about the feedback we received to our non-statutory consultation in our Non-statutory consultation report, which is available from our Document library.

What changes were made to the proposals between the non-statutory consultation in 2023 and the statutory consultation in 2024?

In response to consultation feedback and ongoing survey works, we made several changes to our proposals following 2023’s non-statutory consultation. The changes include: 

  • Removing solar development from various locations, including a significant area south of Great Staughton in Site C, where archaeology surveys have identified the probable site of a previously unknown Roman Small Town. We have subsequently added an additional area of solar development in Site C to compensate for the loss of land elsewhere within this section, whilst also removing solar development from two areas within Site B 
  • Identifying an additional location within Site D where the battery energy storage system and internal substation could be located 
  • Changes to the position and alignment of the underground cable corridors between Sites B, C and D, and between Site D and Eaton Socon substation 
  • Changes to proposed accesses, including the removal of two proposed access points along the B645 near Hail Weston, and the addition of two access north of Site D and west of Great Staughton 
  • Consolidating and realigning fencelines across the proposal area, to ensure suitable buffers with public rights of way, avoid development in fluvial flood zones two and three, and to reduce the overall amount of fencing required. 
Where would the battery energy storage system (BESS) be located?

As part of the statutory consultation, we sought views on two locations where the BESS could be located. At the non-statutory consultation in 2022, we proposed to build the BESS at a location within Site C (Option 1). In response to consultation feedback and environmental surveys, we showed an alternative area within Site D (Option 2) where the BESS and an internal substation could be located. 

We have now confirmed our intention to locate the BESS and internal substation in Site D (Option 2), and have removed the alternative location in Site C from our plans.

Why did you show an alternative location for the battery energy storage system (BESS) during the statutory consultation?

Locating the BESS and internal substation within Site D would make it easier to access the site from the local road network during construction and operation, and in the event that the emergency services needed to access the site. However, the quality of the agricultural land at Option 2 is higher than that at Option 1. 

Following the statutory consultation, we have now confirmed our intention to locate the BESS and internal substation at Option 2 and have removed the alternative location at Option 1 from our plans.

What works will be required at Eaton Socon substation?

To connect into the electricity transmission network at Eaton Socon substation, we will need to undertake works in order to facilitate our connection. These works will include building a new circuit breaker, switchgear, metering equipment and cable sealing end. We anticipate that these works would take place within the footprint of the existing substation. 

How will you build the underground cable connections between the different sites and Eaton Socon substation?

We are proposing to lay cables in open trenches, except where there is a need to cross beneath watercourses, vegetation, areas of archaeological constraint, and roads, where we may employ a trenchless solution (such as horizontal directional drilling) instead. 

Open trench construction involves digging trenches, laying underground cabling within these trenches and then recovering the trenches (using the original topsoil and subsoil, where possible).  

Trenchless crossing construction involves installing an underground duct or pipe, such as by drilling underneath the land surface. This approach does not require the removal of the topsoil or subsoil, and therefore minimises disturbance at the surface. 

What’s happening with the archaeology findings in Site C?

Archaeology survey work has identified the probable site of a previously unknown Roman Small Town to the north and east of New Wood within Site C. This archaeological feature is likely to be of national significance, so we applied to the Government for the remains to be scheduled, which should give them protection in perpetuity. The Department for Culture, Media and Sport confirmed that the site has been given scheduled monument status in September 2024. 

As a result of this find, we are no longer proposing to build solar panels on any of the land that has been scheduled. We are instead proposing to seed this area with species-diverse grassland, which would provide ecological benefits and help protect the site from cultivation for the lifetime of the project. Additionally, we will work with Historic England, Cambridgeshire County Council and the landowner on options for how we can maintain this important find in the future. Potential options include providing funding for further research into the findings, along with opportunities for the local community to engage with the findings, such as through planned digs, which would be subject to receipt of Scheduled Monument Consent, and knowledge-sharing events. 

You can read more about our archaeology findings in Chapter 7 of the PEIR, which is available from our Document library.

Why are you proposing to build on high quality farmland?

We have sought to avoid the use of high-quality agricultural land, including that which is classified as ‘best and most versatile’, where possible when developing our proposals. However, there are various constraints, including the general high quality of farmland in the area, the need to remain within 15km of our agreed connection point at Eaton Socon substation, and the topography/nature of some land within our search area, which mean that our proposals do still involve building solar infrastructure on some high-quality farmland. 

How long will it take the project to offset the carbon emissions produced during construction, operation and decommissioning?

We estimate that it would take four years to displace the lifetime greenhouse gas emissions associated with the project. 

You can read more about how we have calculated these figures in Chapter 15 of the Preliminary environmental information report, which is available from our Document library.

How long would the project be operational for?

Our application for development consent will seek permission to operate East Park Energy for a total of 40 years.  At the end of this period, the land on which the project is built will be returned to a condition suitable for return to its original use after decommissioning, with the exception of areas of planting (woodland and hedgerows) which would be retained post-decommissioning. 

How many jobs will the project create?

We estimate that our proposals would generate 20 full-time equivalent (FTE) roles during the operational phase. This would include 12 FTE roles working on site maintenance, five FTE roles working in management and administrative roles, and three FTE roles working in land management (such as landscape and maintenance and agriculture). 

How long will construction and decommissioning take?

Construction of the project is expected to take between 30 to 36 months, whilst decommissioning works are expected to take between 12 and 24 months. 

During what hours will construction activity take place?

We are proposing that construction works will take place between 8am and 6pm, Monday to Friday, and between 8am and 1pm on Saturdays. We are not proposing any construction activity on Sundays or bank holidays. 

Will any Public Rights of Way (PRoW) be closed/impacted because of your proposals?

We are not proposing to permanently close any PRoW as part of our proposals.  

Some temporary diversions of PRoW may be required during the construction phase. Management of PRoW is likely to include the use of fencing to separate public rights of way of construction traffic and activities. At some locations, banksmen would be utilised when construction traffic is required to cross a PRoW. 

During the operational phase it is expected that all PRoW would be maintained on their existing alignment and that no diversions or closures would be required. 

What are your plans to deliver biodiversity net gain?

Our proposals will deliver significantly above the minimum 10% biodiversity net gain required for projects of this type, including through the delivery of: 

  • 197 hectares of species-diverse grassland 
  • 464 hectares of neutral grassland or grazing pasture 
  • 13 hectares of native species woodland 
  • 17 kilometres of native species hedgerow 
  • 350 individual hedgerow trees 

You can read more about our plans to deliver biodiversity net gain in Chapter 7 of the PEIR, which is available from our Document library.

How will you ensure that local communities benefit from your proposals?

We are proposing a Legacy Fund that could provide financial contributions to local projects.  As part of the statutory consultation, we sought views on how this Legacy Fund could be delivered, including different options for the distribution of this funding.  

You can read more about this in Chapter 7 of our Consultation brochure, which is available from our Document library.

The consultation process
How have you consulted on your plans so far?

We held a total of two public consultations on East Park Energy prior to submitting our Development Consent Order (DCO) application. In 2023, we presented our initial plans for the project and sought feedback as part of a non-statutory public consultation. We then held a statutory public consultation on our detailed plans for the project between 24 September and 29 October 2024.

You can read more about how feedback from both rounds of consultation has been considered in the Consultation Report included in our DCO application.

What is a statutory consultation?

Our statutory consultation took place between 24 September and 29 October 2024. The statutory consultation is an important stage in the development process for nationally significant infrastructure projects. Under the Planning Act 2008, it is the legal consultation we must hold before we can submit our application for development consent. 

Who have you consulted?

As part of our statutory consultation, we wrote to everyone in the parishes the project would be located in with a newsletter that provided details of our consultation and signposted to further sources of information. We also wrote to a range of prescribed and non-prescribed consultees, including parish councils, local councillors, technical stakeholders (such as the Environment Agency and Historic England) and hard to reach groups. We also advertised the consultation on social media. 

You can find out more about who we consulted in the Consultation Report included in our DCO application.

What is an Environmental impact assessment (EIA)?

The nature, size and location of our proposals means that we are undertaking an Environmental impact assessment (EIA) when developing our plans. The purpose of this assessment is to assess the likely significant effects (both adverse) and beneficial of our proposals on the environment.  

As part of our statutory consultation, we have a duty to prepare and consult on Preliminary environmental information. We therefore published a Preliminary environmental information report (PEIR) as part of the statutory consultation. 

As part of our development consent order application, we have submitted a more detailed version of the PEIR known as an Environmental statement.

The DCO process
How are you applying for permission to build, operate and decommission the project?

As East Park Energy is a nationally significant infrastructure project (NSIP), we are seeking permission to build, operate and decommission the project through a development consent order (DCO) application. 

A DCO application is a special type of planning application. Unlike most planning applications, the final decision on DCO applications sits with the relevant Secretary of State rather than with the local planning authority. Despite this, local councils remain a key consultee throughout the application process. 

You can read more about the DCO process on the Planning Inspectorate’s website here. 

How can I take part in the Examination process?
As part of the Pre-examination phase, the relevant representation period is now open. This is your opportunity to take part in the Examination process by registering as an interested party and submitting a written summary of your views. The registration period opened on Wednesday 26 November 2025, and will close at 23:59 on Wednesday 14 January 2026. To register, you can submit a relevant representation via the Planning Inspectorate’s website. You can read more about the DCO process on the Planning Inspectorate’s website here. 

Get in touch

Call us on the community information line:
0808 258 5991

(Line open Monday to Friday, 9am to 5.30pm)

Write to us:
Freepost EAST PARK ENERGY

(Please note, no stamp or further address details are required)